Key takeaways
- An option agreement binds the landowner while the developer stays free to decide, since the company holding the option is not bound and may choose whether to exercise it, per Michigan State University Extension.
- Extension guides describe solar leases that typically run 20 to 30 years or more and wind operating leases of 20 to 30 years, so a lease signed this year can run well past a landowner’s current farming plans.
- Decommissioning security can take the form of an escrow, letter of credit, bond or corporate guaranty, and the guide advises that it be available on abandonment or early termination.
- In Idaho, a special use permit is set by county ordinance and conditions and is not transferable from one parcel to another, so permit conditions and lease terms have to be read side by side.
- Idaho forfeits a water right that isn’t applied to beneficial use for five years, subject to twelve listed exceptions, which matters when a project takes irrigated ground out of production for decades.
What is a solar or wind land lease, and why does it start with an option?
A solar or wind land lease is a long-term agreement that lets an energy developer use a landowner’s ground for generating equipment, access roads and power lines, and it usually starts with an option because the developer needs time to find out whether the project can be built before it commits to the land. The developer studies the site, applies for approvals and lines up a buyer for the power. The landowner, meanwhile, signs something that holds the land for it.
Michigan State University Extension describes the structure plainly. The company that holds the option, in the guide’s words, “is not bound but instead may choose whether or not to exercise the option,” while the option period itself is binding on the landowner (Walker, Agricultural Solar Energy Development). That asymmetry is the whole reason the option stage gets the attention in this article. After it’s signed, the landowner has already agreed to hold the land and, in many cases, to the lease form attached to it.
An option agreement is a paid right, usually for a set period, that lets a developer decide later whether to lease or buy the land on stated terms, while the landowner stays bound to keep the land available for it.
Decommissioning security is money or credit, such as an escrow, letter of credit, bond or corporate guaranty, set aside so the cost of removing the equipment and restoring the land doesn’t fall on the landowner.
Much of what follows draws on university extension guides written for landowners in Michigan, Ohio, Wisconsin and Indiana, because they are among the most thorough public descriptions of how these leases are built. They are out-of-state and general. Where Idaho law changes the answer, we cite the Idaho Code directly and say so.
Has a developer or land agent contacted you about an option? A short call before anything is signed will tell you which terms are open and which become hard to change once the option is in place.
Book Your Free Legal-Strategy CallHow long is the option period, and what does a landowner give up during it?
The option period can be as short as a single year with renewals or as long as five, seven or even ten years, and during it the landowner generally gives up the freedom to sell, lease or encumber the land on terms that conflict with the developer’s rights. Purdue Extension’s wind guide describes options running “five, seven or even 10 years” or “as little as a single year” with developer renewal options, and says the payment is usually “a fairly modest payment, usually on a per-acre basis” (Emanuel and Martin, A Landowner’s Guide to Commercial Wind Energy Contracts).
Two features deserve attention. The first is the payment, which Michigan State Extension says must be some form of consideration, “usually money,” to make the option legally binding, and which may be a lump sum. A modest payment spread over a long option can look small each year and still add up to a long commitment. The second is renewal. A one-year option with developer-controlled renewals can stretch as far as a seven-year one, without the landowner ever having agreed to seven years in so many words.
What the landowner can still do with the land
University of Wisconsin Extension raises a practical question that is easy to skip: “if the project is delayed, can you still farm the land?” (UW-Madison Extension, Solar Land Leasing Contracts). An option that doesn’t answer that leaves the farming rights to argument. So does one that is silent on crop damage. Michigan State Extension says there should be a written provision for payment if the company exercises the option and the crops can’t be harvested or sold.
Then there is the mortgage. Michigan State Extension notes that granting a new interest in the property may be a default under the loan, so permission from the lender may be needed, and the lender may ask for a subordination agreement with the tenant. The lender is better asked before signing than after the option is already in place. Our piece on lease assignment and subletting covers the related tenant-side concepts.
The attached lease form
Some options attach the full lease form as an exhibit, so the landowner knows what the lease will say if the developer proceeds. Others describe the lease only in outline and leave the rest to be agreed later. The first is the safer shape for the landowner, since every term in the exhibit has already been seen. The second leaves the landowner holding the land for a developer while the terms that matter are still blank. If a bargaining position exists, it exists at this stage, because the developer wants the option signed.
How do lease term, rent and escalators work over 25 years or more?
A solar or wind lease usually runs 20 to 30 years or more, rent is calculated per acre, per megawatt or as a share of revenue, and an escalator raises the payment by a fixed amount or by an outside index. Michigan State Extension states that “solar leases typically run from 20 to 30 years or more,” and Purdue Extension says wind operating leases “generally are for a period of 20-30 years.” The table summarizes the main terms and the question each one raises.
| Term | What the extension guides describe | Question for the landowner | Why it matters |
|---|---|---|---|
| Option period | One year with renewals, or five, seven or ten years | Who controls renewal, and what is paid each year? | A long option holds the land while the developer decides. |
| Operating term | 20 to 30 years or more; wind similar; solar initial terms often 25 to 30 years | Can the developer extend alone? | An automatic extension can double a commitment the landowner thought was fixed. |
| Rent basis | Per acre, per megawatt, or percentage of revenue; wind adds fixed, royalty or combined models | Which measure applies, and when does rent start? | Rent “likely will not begin until sometime after signing the lease.” |
| Escalator | A pre-set amount, or a percentage tied to inflation or another outside measure | Is there one, and what is it tied to? | A flat payment loses value over a multi-decade term. |
| Termination rights | Many leases let the developer end the lease at any time and do not give the landowner the same right | Who can leave, when, and at what cost? | The right to walk away is worth more than the rent. |
| Assignment | Typically allowed to a successor without landlord consent | Does the original tenant stay liable? | The party who signs may not be the party who operates. |
Termination is the row that draws the most attention in the guides. University of Wisconsin Extension observes that “many leases allow developers to end the lease at any time, but do not allow landowners to terminate,” and that initial terms are usually 25 to 30 years, often with a clause letting the developer extend without new landowner approval. Whether a particular lease works that way is a matter of reading it. The point of the table is that each row is a negotiating item, and the guides treat them that way.
Idaho agricultural assessment
Taxes are the next question. Idaho Code makes land eligible for agricultural assessment when it is “actively devoted to agriculture,” and for tracts over five acres that means uses such as field crops, nursery stock, for-profit livestock grazing or cropland retirement programs (Idaho Code 63-604). What the county assessor will do with acres under panels is a question for the county and the facts of the parcel. Michigan State Extension, writing about Michigan, says a commercial solar installation may cost a parcel its agricultural status, and suggests that the lease make the tenant pay the resulting additional taxes and that a separate parcel be created for the lease area. Whether that works in Idaho depends on county practice, so it belongs in the pre-signing checklist.
How do setbacks, access and easements affect a working farm?
Setbacks, access and easements decide how much of the remaining farm keeps working, because the lease and its easements control where equipment sits, where roads and lines run, and what the landowner may still build or plant nearby. Michigan State Extension advises landowners to avoid “exclusive” easements, which “prohibit any use of the easement area by the landowner or others,” and notes that negotiation “may be necessary to limit the areas included and minimize any impacts on farming, including underground uses and overhead interference with equipment.”
Several practical items repeat across the guides. Wisconsin Extension points to drainage tile and asks that the developer be responsible for repairs, access and reimbursement. It also asks for a right of entry to other land the owner farms. Purdue Extension, on the wind side, asks about crop and land damage, “particularly compaction,” notes that developers are “more flexible in siting access roads than turbines,” and describes contracts that commit the landowner to a turbine location “completely at the developer’s discretion and without any input.” Each of these is a negotiable line, and each is easier to change before the option exists.
County permits are separate from the lease
In Idaho, counties regulate where these projects go through zoning, and one route is a special use permit. Idaho Code 67-6512 says a special use permit may be granted when the use is conditionally permitted by ordinance and not in conflict with the plan, and it lets a county attach conditions such as “controlling the duration of development” and “designating the exact location and nature of development” (Idaho Code 67-6512). It also says a special use permit is not transferable from one parcel of land to another. Two consequences follow. A county’s setback and location conditions can reshape the project after the lease is signed, and the lease should say what happens to payments and acreage when they do. And a landowner who agrees to a lease area has to know the permit attaches to that parcel.
We cover the county side in zoning and land use and the easement side in easements and access rights.
Easements, solar access and transmission
Idaho recognizes a solar easement as a written easement for the purpose of exposing a solar energy device to sunlight, and the statute says the writing must state the vertical and horizontal angles, the terms on which the easement is granted or ends, and any compensation provisions (Idaho Code 55-615). Separately, Idaho Code 55-603 provides that easements in gross of a commercial character, a category that includes transmission of electricity, may be transferred or assigned “in accordance with the express language of the instrument” (Idaho Code 55-603). The instrument’s own words decide who can assign it. That makes the assignment clause in any collection-line or transmission easement worth reading as carefully as the lease itself.

Looking at a draft lease with access, setback and easement language? Send it and we will mark the clauses that touch the rest of your operation.
Book Your Free Legal-Strategy CallWho pays to remove the equipment, and how is that secured?
Whoever signs the lease usually owes the removal, but that obligation is only as good as the money or credit behind it, which is why the security term matters more than the removal clause. Michigan State Extension advises that the lease say decommissioning means “removal of its structures and debris along with restoration of your land similar to its original condition, including soil and vegetation,” and that security can take the form of “an escrow, letter of credit, bond, or corporate guaranty.” It adds that the decommissioning resources should be available “upon abandonment of the project or any early termination of the lease.”
The Wisconsin guide asks the sharper question: “who pays if the developer sells or goes bankrupt,” and notes that landowners “may require escrow funds or a removal bond.” Both guides present security as something the landowner asks for, which is a fair signal that it isn’t automatic in every form. If a lease can be assigned without consent, and the guides say that is typical, the security needs to survive the assignment. Michigan State Extension says a landowner may be able to negotiate for the original tenant to remain liable after assigning.
What gets removed, and from how deep
The U.S. Department of Energy’s wind end-of-service guide says a decommissioning plan “is usually conducted as part of the original project development,” and that foundations and cables are “typically left in place in the ground below a depth (usually 3–5 feet) that is agreed upon by the community/landowner and project owner(s)” (DOE, Wind Energy End-of-Service Guide). The depth is a negotiated number, then, and farm equipment, tile lines and future crops all reach into the same soil. The guide doesn’t prescribe a figure for a particular farm, and nothing here replaces reading the removal depth in the lease.
What happens to solar panels
The U.S. Environmental Protection Agency says that “some solar panels are considered hazardous waste, and some are not, even within the same model and manufacturer” (EPA, End-of-Life Solar Panels). The Department of Energy adds that the total cost of recycling is generally greater than the cost of landfill disposal (DOE, End-of-Life Management for Solar Photovoltaics). Put the two together and the removal bill may depend on how the panels are classified and what disposal route the market allows when the lease ends decades from now. A security amount fixed on signing day may not match that world, so whether it’s re-estimated over time is a term worth raising.
What is a sensible order for reviewing a developer’s option and lease?
A sensible order is to get the whole lease form first, map the land and its encumbrances, check the county, tax and water-right consequences, negotiate the exit and the security before the money, and have an attorney and a CPA review the package before anything is signed. Each of the three extension guides cited here recommends outside review. Purdue Extension describes wind contracts as complex documents that have the landowner agree to certain property uses for an extended period, and recommends review by an attorney experienced in property and contract law.
- Get the full lease form and every exhibit before signing the option. An option that refers to a lease “to be agreed” leaves the terms that matter open while the land is held. Ask for the form, the maps and the security terms in writing.
- Map the land and what encumbers it. List the acres, access routes, drainage tile, irrigation works, the mortgage and any existing leases or easements. Ask the lender about permission and a subordination agreement before the option is in place.
- Check the public consequences. Ask the county how a special use permit would work for the parcel, ask the assessor how acres under equipment are treated for agricultural assessment, and read the water right’s status before irrigated acres come out of production.
- Negotiate the exit and the security before the rent. Termination rights, decommissioning security, assignment and the removal depth cost the developer little to discuss now and a great deal to change later.
- Get legal and tax review of the whole package. Michigan State Extension recommends both an attorney and a CPA, and Wisconsin Extension notes that some developers cover attorney fees for lease review while the landowner picks the lawyer.
The option binds the landowner for years. The developer decides later whether it’s bound at all.
Water: the term that is easy to leave out
Idaho Code 42-222 provides that a water right is lost and forfeited by a failure for five years to apply it to the beneficial use for which it was appropriated, and that the party asserting forfeiture has the burden of proving it by clear and convincing evidence (Idaho Code 42-222). The same section requires approval from the Idaho Department of Water Resources before a change in place or nature of use. Section 42-223 then lists twelve exceptions to forfeiture, including a federal cropland set-aside program, circumstances beyond the owner’s control and resumption of use before a third party makes a claim (Idaho Code 42-223). A 25-year lease on irrigated ground covers far more than five years. Whether any exception fits a given project is a question for the water right’s owner and counsel, and the lease should say who protects the right. We cover the larger picture in water rights and land use for Idaho farms.

For the lease form itself, our explainer on ground leases covers the general building blocks, and our agricultural practice in Idaho is where a developer’s offer to a farm or ranch gets reviewed.
Key terms
- Escalator
- A clause that raises rent over the life of a lease, either by a pre-set amount or by a percentage tied to inflation or another outside measure.
- Easement in gross
- An easement that benefits a person or company rather than a neighboring parcel of land, such as a utility’s right to run power lines across a property.
- Subordination agreement
- A document in which a lender agrees that its mortgage ranks behind, or won’t disturb, another party’s interest in the land, such as a developer’s lease.
What does an option offer look like from the landowner’s side?
The problem
A land agent offers a modest annual payment per acre for a seven-year option. The payment looks small, the farm keeps running and the lease form is described as standard. Nothing in the pitch mentions who can end the lease, what secures the removal cost or whether the lender has to agree.
The solution
We read the option and the attached lease together, mark the terms that bind you before the developer commits, check the county, tax and water-right consequences, and propose changes in the order they’re lowest-cost to win: exit, security, access, then rent.
The resolution
You get a clear view of what the option really commits you to. If you’ve already decided to turn the developer down, you don’t need a lawyer for that. And if a developer offers to cover lease review, you still choose your own counsel; it doesn’t have to be us.
About the author

Co-founder of Clark Meyers PC, lead trial counsel, and a private mediator and arbitrator since 2008. He has served as a court-appointed arbitrator in Santa Clara County and as Judge Pro Tem in the San Mateo County Superior Courts, and handles complex commercial disputes, contract claims and real estate conflicts.
Reviewed by

Co-founder of Clark Meyers PC and a Notre Dame Law School graduate who also serves as CEO and General Counsel of ACE Building Envelope Design and Chief Legal Officer of ZEA Biosciences. He has run companies as well as advised them, across construction, design, forensic investigation and biotech. Reviewed this article for legal accuracy on October 30, 2026.
How we check this work
Idaho statements come from the Idaho Code on legislature.idaho.gov. Descriptions of typical lease structures come from university extension guides in Michigan and Ohio, Wisconsin and Indiana, which are general and not Idaho-specific, plus U.S. Department of Energy and U.S. EPA pages. No payment or cost figures are stated. Reviewed by a Clark Meyers attorney before publication.
Sources
- Walker, Wendy K. “Agricultural Solar Energy Development: Understanding Lease Agreements for Utility-Scale Installations.” Michigan State University Extension, March 2019 (hosted by Ohio State University’s Energize Ohio). https://energizeohio.osu.edu/sites/energizeohio/files/imce/Agricultural%20Solar%20Energy%20Development%20Understanding%20Lease%20Agreements%20for%20Utility-Scale%20Installations.pdf
- University of Wisconsin-Madison Division of Extension. “Solar Land Leasing Contracts.” https://economicdevelopment.extension.wisc.edu/reset/solarleasingcontracts/
- Emanuel, Curt, and Chad Martin. “A Landowner’s Guide to Commercial Wind Energy Contracts.” Purdue Extension, 2012. https://www.extension.purdue.edu/extmedia/ABE/RE-5-W.pdf
- U.S. Department of Energy, WINDExchange. “Wind Energy End-of-Service Guide.” https://www.energy.gov/eere/wind/windexchange/wind-energy-end-service-guide
- U.S. Department of Energy, Solar Energy Technologies Office. “End-of-Life Management for Solar Photovoltaics.” https://www.energy.gov/cmei/systems/end-life-management-solar-photovoltaics
- U.S. Environmental Protection Agency. “End-of-Life Solar Panels: Regulations and Management.” https://www.epa.gov/hw/end-life-solar-panels-regulations-and-management
- Idaho Legislature. Idaho Code, Title 67, Chapter 65, Section 67-6512. https://legislature.idaho.gov/statutesrules/idstat/title67/t67ch65/sect67-6512/
- Idaho Legislature. Idaho Code, Title 63, Chapter 6, Section 63-604. https://legislature.idaho.gov/statutesrules/idstat/title63/t63ch6/sect63-604/
- Idaho Legislature. Idaho Code, Title 55, Chapter 6, Section 55-615. https://legislature.idaho.gov/statutesrules/idstat/title55/t55ch6/sect55-615/
- Idaho Legislature. Idaho Code, Title 55, Chapter 6, Section 55-603. https://legislature.idaho.gov/statutesrules/idstat/title55/t55ch6/sect55-603/
- Idaho Legislature. Idaho Code, Title 42, Chapter 2, Section 42-222. https://legislature.idaho.gov/statutesrules/idstat/Title42/T42CH2/SECT42-222/
- Idaho Legislature. Idaho Code, Title 42, Chapter 2, Section 42-223. https://legislature.idaho.gov/statutesrules/idstat/title42/t42ch2/sect42-223/
Last reviewed: October 30, 2026 · What changed: First publication.
This article is general information about the law, not legal advice, and it is not a substitute for advice from a lawyer about your specific situation. Reading it does not create an attorney-client relationship with Clark Meyers PC. Laws change and apply differently depending on the facts and the state involved.
Licensed to practice in Idaho (Idaho State Bar) and California (Bar #175238). Licensed to practice in California (Bar #157601). Clark Meyers PC does not offer legal advice in states where its attorneys are not licensed. This page may be considered attorney advertising in some jurisdictions.
Frequently asked questions
How long does a solar land lease usually last?
Michigan State University Extension says solar leases typically run from 20 to 30 years or more, and University of Wisconsin Extension describes initial terms of 25 to 30 years, often with a developer right to extend. That is the operating term, and it comes after the option period. Some leases include automatic or notice-triggered renewals. A landowner reading a lease should add the option, the operating term and every extension to see the full commitment.
What is an option period, and why does it matter?
An option period is the time during which a developer holds a paid right to decide whether to lease the land, and it matters because the landowner is bound during it while the developer is not. Purdue Extension describes options of five, seven or ten years, or a single year with renewals. During that time the landowner generally can’t commit the land to anyone else. The payment is usually modest, so the real cost is the time the land is tied up.
How is rent calculated on a solar or wind lease?
Michigan State Extension says solar rent is ordinarily calculated per acre, per megawatt produced or as a percentage of power sales revenue, and Purdue Extension describes wind payments as fixed, royalty or a combination. Rent is usually paid once or twice a year, and the guide notes it likely won’t begin until some time after signing. An escalator can raise it over time. Which model fits depends on the project and the landowner’s priorities.
Can the landowner end the lease early?
It depends on the lease, and University of Wisconsin Extension observes that many leases let developers end the lease at any time but do not let landowners terminate. A landowner’s exit right, if any, often depends on a developer default that the lease defines and a cure period the lease allows. That is why termination rights belong at the top of the list. If the lease has no landowner exit, the landowner’s practical remedy is a default claim.
What forms can decommissioning security take?
Michigan State Extension lists an escrow, a letter of credit, a bond or a corporate guaranty as the forms security from the tenant can take. Each has different strengths. An escrow or letter of credit is cash or bank credit set aside. A guaranty depends on the guarantor’s finances later. The guide advises that the resources be available on abandonment or early termination, so the trigger language matters as much as the form.
Will a solar or wind lease affect agricultural property tax in Idaho?
It may, but the answer depends on the county’s treatment of the specific parcel, because Idaho Code 63-604 makes land eligible for agricultural assessment when it is actively devoted to agriculture. For tracts over five acres that means uses such as field crops, nursery stock or for-profit livestock grazing. How the assessor treats acres under equipment is a county question. The lease can allocate any resulting tax change, and a CPA can model it.
Does a solar or wind project on irrigated land put the water right at risk?
It can raise the question, since Idaho Code 42-222 provides that a water right is forfeited by a failure for five years to apply it to beneficial use, unless an exception applies. Section 42-223 lists twelve exceptions, and a change in place or nature of use requires prior approval from the Idaho Department of Water Resources. Whether a particular project falls inside an exception is a fact question. The lease should say who protects the right.
Can the developer sell or assign the lease to someone else?
Usually yes, since Michigan State Extension says assignment to a successor is typically allowed without the landlord’s consent, though a landowner may be able to negotiate for the original tenant to remain liable. For transmission and similar commercial easements, Idaho Code 55-603 says they may be assigned in accordance with the express language of the instrument. The assignment clause is therefore a negotiated term, not a formality. The company that signs the lease and the company that operates the project can end up being different.
The short version
A solar or wind lease is a decades-long commitment that starts with a short, quiet option. The landowner’s strongest negotiating room sits before that option is signed: who can exit, what secures removal, how access and permits fit the rest of the farm, and what happens to the water right and the tax status. Rent is the last term to haggle over.
Keep reading
More on this across our guides.
A Legal Guide for Idaho Farmers and Ranchers
The contracts, land-use rules and water questions that sit behind a working Idaho farm.
EasementsEasements and Access Rights
How access easements are created, scoped and assigned.
Land useZoning and Land Use
How counties decide where a project can go and on what conditions.
WaterWater Rights and Land Use for Idaho Farms
What happens to a water right when land use changes.